State of Tasmania v Leighton Constructions Pty Ltd [2005] TASSC 133

You are here:
< Back
Facts
  • Leighton Construction entered into a contract with the State of Tasmania to build a new stretch of highway. The estimated cost of the contract was $30,000,000
  • There was a liquidated damages clause in the contract which made Leighton liable for $8,000 for each day it was over the deadline.
  • Leighton was significantly over the deadline, and when Tasmania tried to enforce the LD clause, they sued, saying it was actually a penalty clause.
Held
  • It was a penalty clause (at first instance) but it was NOT a penalty clause at second instance in the supreme court.
  • It was not a penalty clause because it was not an “exorbitant”, “unconscionable” etc
  • It was comparable to the actual costs which is a key fact
  • Aside from the actual cost of hire, you have to look at other factors like how much it costs for the state to keep the roads open (‘notional interest’)
  • Public utility is also a consideration

-- Download State of Tasmania v Leighton Constructions Pty Ltd [2005] TASSC 133 as PDF --


FavoriteLoadingSave this case